A dated record of meaningful public developments reflected in the project tracker, with a supporting source for each entry.
EnablerBasic Infrastructure
Coastal Road Network & Second Trunk Road
Batang Paloh Bridge opened to traffic on 30 October 2026 and Batang Lupar 2 opened on 31 October 2026. Batang Saribas 2 is targeted to open on 5 December 2026. Sejingkat Bridge contractual completion and Rambungan Bridge stay open.
Deputy Minister Rosey Yunus said OSEIC Miri is scheduled to begin operations in November 2026. The open operations milestone was revised from 2027 and stays incomplete until opening is confirmed.
Besra's September 2026 quarterly reported a preferred three-year investigation and study programme for the Jugan lease. Final mining lease conditions remain open. Status stays Planning.
UKAS reported SSLR Phase 1 at 78.07 percent and Phase 2 at 23.38 percent as of 21 October 2026. The open Phase 2 completion target moves to 2030. Phase 1 completion in March 2027 stays open. The displayed value stays RM7.6 billion for Phase 2 only.
Budget 2027 allocated RM20.47 million for paddy expansion. The open 2027 milestone now names Phase 1 across seven areas covering about 2,000 hectares. Farmer clustering and the 2030 output target stay open.
SMD Semiconductor said Linyang keteq.GaN chip integration is planned to begin in 2027. Global IP registration and commercialisation remain open. The value stays Not disclosed.
UKAS set Batang Lupar 2 traffic opening for November 2026 and Batang Saribas 2 completion for December 2026. Rambungan Bridge opening in 2026 stays open from existing Star coverage. Sejingkat contractual completion, Batang Paloh traffic opening, and the remaining nine major bridges stay open.
The Edge Malaysia reported that the Singapore interconnection is in a submarine cable survey study. Remaining licences, commercial close, and the 2032-2035 export window stay open.
The Edge Malaysia reported Q4 2027 completion for the Miri CCGT plant, refining the open completion date. The displayed value stays RM2 billion; UKAS RM2.5 billion remains held for manual review.
UKAS reported that a Tanjung Embang coordinating task force was established. Physical development is targeted to begin in early 2027 through PPP, and Samajaya 2 High Tech Park readiness for investors in 2028 is open. The hub-wide value stays Not disclosed.
DayakDaily reported that 10 paddy projects covering 3,460 hectares are under implementation. Phased project completion from 2027 is open. Farmer clustering and the 2030 output target stay open.
Borneo Post reported that Selangau Pig Farming Area operations are targeted for 2027. Basic site infrastructure in 2028 stays open. The displayed value stays RM300 million; a 20 October Borneo Post RM200 million figure is held for manual review.
DayakDaily reported that DUS confirmed the design-and-build tender is still live, with Surat Setuju Terima (SST) targeted for Q1 2027 and completion in 2032. The displayed value stays RM1.52 billion.
Borneo Post reported that the Airport Development Request was submitted to the federal Ministry of Transport on 26 May 2026. Federal approval and 2027 construction remain open. Status stays Planning.
Borneo Post and DayakDaily reported that the Samarahan campus reached 90 percent completion and that the project value is RM320 million. Official launch in Q3 2027 remains open.
UKAS and DayakDaily reported Phase 1 at 49 percent progress and Blue Line Phase 1 from Rembus to Northbank at 88 percent physical progress. ART pilot service in Q4 2026 and commercial service in 2027 remain open.
ADUN Telang Usan urged faster approval of the Temala Line-In-Line-Out (LILO) grid-connection substation so Baram agrovoltaic solar generation can connect to the state grid. The LILO approval remains an open milestone.
UKAS reported that the 500MW Miri CCGT project reached 63 percent completion as of the third quarter of 2026. Commercial operations remain targeted for the end of 2027. The displayed value stays RM2 billion; UKAS also stated RM2.5 billion, which is held for manual review.
Premier Abang Johari said PETROS is constructing the about 65 km Kidurong to Samalaju gas pipeline, and that Samalaju would receive gas supply once the project is completed at the end of 2026. That schedule supersedes the earlier progressive commercial operations target from 2027.
JKR Sarawak completed the final structural connection of the Batang Paloh Bridge on 8 October 2026 during a stitching ceremony. The Coastal Road Package 03 bridge is targeted to open to traffic on 30 October 2026. Sejingkat contractual completion and the remaining major bridges stay open.
Premier Abang Johari said about 7,000 hectares of State land have been gazetted exclusively for paddy production within the wider 14,000-hectare paddy programme. Farmer clustering and land leasing remain open.
The Auditor General's Report 2/2026 said Work Package 11 at Lambir was 99.9 percent complete as of 31 March 2026. An extension of time granted on 27 July 2026 moved full completion to 31 December 2028, superseding the earlier first-quarter 2029 target.
Premier Abang Johari unveiled keteq.GaN, SMD Semiconductor's locally designed gallium nitride power chip, at the opening of IDECS 2026. Global IP registration and commercialisation remain open.
The Sejingkat Bridge opened to the public on 5 October 2026 after a soft-opening ceremony. Contractual completion on 22 October and the rest of the CSTR programme remain open. The remaining nine major bridges are targeted for late 2027.
PETROS entered a Joint Development Agreement with Höegh Evi for the Kuching LNG Terminal as part of the Kuching Low-Carbon Hub, targeting first gas by the end of 2029.
JKR Sarawak said the Sejingkat Bridge will open to road users at 10am on 5 October 2026, following a pre-opening ceremony. The earlier 1 October traffic target is superseded.
Miri Port Authority said the Kuala Baram dredging project had reached about 90 percent physical progress on 21 September 2026 and was ahead of the contract schedule. Completion is expected by the end of 2026.
The SCORE card now matches existing public reporting: May 2025 investment attracted and jobs created, 243 rural infrastructure projects underway, and a 2030 Miri–Marudi–Mulu road completion target.
SIDC's CEO said the Samarahan facility is scheduled for official launch in the third quarter of 2027, superseding the earlier October 2026 campus-completion target.
M-FICORD, SLDB and the Department of Agriculture opened commercial participant applications for SARTECH Semenggok, closing on 30 September 2026. Site-development completion stays open.
Sarawak Metro said the final girder was installed for the 400-metre dedicated ART bridge across Sungai Kuap. ART pilot service in the fourth quarter of 2026 remains open.
Bintulu Development Authority handed the community support centre keys to the ministry, which authorised SORCS to manage the centre. Operations are expected by the end of 2026.
SMD Semiconductor and Jiangsu Linyang Energy signed an MoA covering technical evaluation, integration, qualification and commercialisation of Sarawak-developed power-semiconductor technologies.
Construction of the Sarawak Bioindustrial Park Central Hub officially commenced after the foundation-laying ceremony, and BioVerde exchanged eight industry collaboration agreements and MoUs. The 24-month construction period targets completion in August 2028. Anchor and research partner selection remains open where partners are still exploring facilities.
POWERCHINA reported that first-bay concrete for the Baleh dam face slab was poured on 10 August 2026, marking the start of main face-slab construction. Reservoir impoundment from September 2027 and later generation milestones remain open.
Premier Abang Johari formally launched AgriHub Gedong at COSAFS2026, alongside AgriHub Layar and AgriHub Marudi. AgriHub and irrigation works completion at Lubok Punggor stays open.
Gladioli Group formally accepted the conditional renewal offer for Mining Lease ML 05/2012/1D. Engagement with Sarawak authorities continues on the final renewal terms.
Eighty artificial reef balls were deployed at Kuala Nyalau-Samalaju, while SFC reported a long-term statewide target of 5,000 units through continuing marine-conservation partnerships.
The five-storey Sarawak Science Centre officially launched with 22 thematic galleries and more than 400 hands-on exhibits, before opening to visitors on 30 July.
A RM328 million EPCC contract was awarded for the 100MWac agrivoltaic solar facility in Phase 1, marking the project's move from approvals and site preparation into execution.
The minister said OSEIC Miri would begin operations in 2027 as Sarawak's third centre after Kuching and Dalat, superseding the earlier 2026 opening target.
Sarawak Rivers Board recorded 69 percent overall progress as of 30 June 2026, three percentage points ahead of schedule, while October 2026 completion remains the open target.
The Samalaju SME Cluster was officially launched, with Phases 1 and 2 already completed at a cost of RM25.8 million and providing 21 industrial lots out of a planned 10 phases.
JKR Sarawak awarded the combined delivery-package tender for the Sarawak Bioindustrial Park and SBC Bioprocess Commercial Centre, moving the bundled project into implementation.
JKR reported SSLR Phase 1 at 71.16 percent completion and Phase 2 at 11.39 percent physical progress as of 11 June 2026, with Phase 1 completion scheduled for 16 March 2027.
The RM30 million first phase was announced for Samarahan, combining early intervention, vocational training, therapy and trainee accommodation, with completion targeted for May 2028.
The Premier said the detailed KLCH masterplan was still being finalised, with physical and infrastructure development expected to begin in 2027 through a public-private partnership.
UKAS reported the Premier saying KLCH physical and infrastructure works, including the New Kuching International Airport, are expected to begin in 2027 through PPP. Federal Airport Development Request approval stays open.
UKAS reported the Premier saying KLCH physical and infrastructure works, including the deep-sea port, are expected to begin in 2027 through PPP. Port and gas-terminal operations in 2032 stay open.
The site-verification and feasibility study was completed, confirming Tanjung Embang as operationally and technically feasible. The project is proceeding to a federal Airport Development Request.
Utility Minister Julaihi told the DUN that commercial discussions and technical development had commenced after National Security Council approval in December 2025 and Singapore Maritime and Port Authority approval in February 2026.
KUTS Phase 1 reached 38.2 percent physical progress by 30 April 2026. Pilot operations are scheduled for the fourth quarter of 2026 before full commercial operations in 2027.
The Sarawak Legislative Assembly passed the Sarawak Padi and Rice Board Bill, 2026, creating the statutory basis for a state padi and rice board. Farmer clustering, land leasing, and the 2030 output target remain open.
The Sarawak Government reported RM5.743 million in development grants and assessed progress at the OSEIC Miri site in Tudan ahead of its planned opening.
The Deputy Premier said approved investments in SCORE had reached RM151.5 billion across 655 projects, with the potential to generate more than 60,000 jobs.
The proposed RM6 billion Baram Agrovoltaic Project scope was announced for Temala near Long Lama, combining renewable energy, commercial agriculture, logistics and township components.
Gas pipelines were installed to about 122 homes and public facilities in Kampung Teh and Kampung Tabo, with the pilot project targeted for completion by the end of 2026.
Compensation totalling RM6.5 million was handed to 119 recipients for the Lubok Punggor AgriHub development, whose scope includes irrigation, drainage, a reservoir, warehouse and machinery workshop.
RM30 million in development funding and the marine eco-tourism scope were confirmed for the Piasau discovery centre. Completion is scheduled for August 2027.
The Premier said the Climate Change Centre will be placed under the new Climate and Energy Diplomacy Unit as its technical arm. The centre is not yet operating as a standalone institution.
DID Sarawak reported that land clearing for production plots at SARTECH Tarat and Semenggok had been fully completed, and that the Sarawak Land Development Board had been appointed as the managing agent.
The Samarahan campus reached 40.19 percent physical progress in October 2025, while the SIDC research organisation continued operating ahead of the campus completion target.
Budget 2026 allocated RM25.1 million for rehabilitation of the Mid Sadong 1 (Lubok Punggor) Scheme. The card's RM30 million initial project value is unchanged.
Parliamentary reporting placed the project's preliminary estimate above RM500 million and potentially up to RM1 billion, pending finalisation after preliminary work expected by the end of 2026.
NREB confirmed that the Flaring and Venting Rules 2025 came into force on 1 November 2025 and require prior consent for flaring and venting. Annual verified emissions reporting remains open.
The ASEAN Centre for Biodiversity confirmed Bako National Park as the 65th ASEAN Heritage Park, recognising its outstanding biological and conservation significance.
The ASEAN Centre for Biodiversity confirmed Lambir Hills National Park as the 66th ASEAN Heritage Park, recognising its exceptional plant diversity and conservation importance.
At the Phase II final deployment ceremony in Kabong, Sarawak Forestry Corporation said all 5,000 Phase II reef balls had been deployed along the Sarawak coastline. Phase II programme completion in 2027 remains open for monitoring and socio-economic studies. The later July 2026 Kuala Nyalau 80-unit drop is recorded separately as continuing activity.
The Sarawak Government reported a RM1 billion allocation for the Stumbin-Bijat paddy project, covering irrigation, drainage, farm roads, and related infrastructure.
PT Kayan Hydropower Nusantara said access roads were completed and restated a 2030 commercial-operation target, with financial close still pending confirmation after the earlier Q1 2026 aim.
Construction of the RM300 million Selangau Pig Farming Area began with a groundbreaking ceremony at Sungai Selabi, on a 232.69-hectare site designed for 12,000 parent stock.
Ongoing Bintulu studies by SEDC Energy and PETRONAS were publicly confirmed alongside a plan to scale microalgae cultivation to 10,000 acres and support a later bio-refinery.