Sarawak Development Monitor

PCDS 2030Tracker Updates

A dated record of meaningful public developments reflected in the project tracker, with a supporting source for each entry.

EnablerBasic Infrastructure

Coastal Road Network & Second Trunk Road

Batang Paloh Bridge opened to traffic on 30 October 2026 and Batang Lupar 2 opened on 31 October 2026. Batang Saribas 2 is targeted to open on 5 December 2026. Sejingkat Bridge contractual completion and Rambungan Bridge stay open.

Source: DayakDaily — Batang Paloh Bridge opens to traffic (Oct 2026)
EnablerBasic Infrastructure

Coastal Road Network & Second Trunk Road

UKAS set Batang Lupar 2 traffic opening for November 2026 and Batang Saribas 2 completion for December 2026. Rambungan Bridge opening in 2026 stays open from existing Star coverage. Sejingkat contractual completion, Batang Paloh traffic opening, and the remaining nine major bridges stay open.

Source: UKAS — Batang Lupar 2 and Batang Saribas 2 schedules (Oct 2026)
EnablerBasic Infrastructure

Kuching Low-Carbon Hub

UKAS reported that a Tanjung Embang coordinating task force was established. Physical development is targeted to begin in early 2027 through PPP, and Samajaya 2 High Tech Park readiness for investors in 2028 is open. The hub-wide value stays Not disclosed.

Source: UKAS — Tanjung Embang coordinating task force (Oct 2026)
SectorCommercial Agriculture

Selangau Pig Farming Area

Borneo Post reported that Selangau Pig Farming Area operations are targeted for 2027. Basic site infrastructure in 2028 stays open. The displayed value stays RM300 million; a 20 October Borneo Post RM200 million figure is held for manual review.

Source: Borneo Post — Selangau PFA operations targeted for 2027 (Oct 2026)
SectorSocial Services

Sarawak Cancer Centre

DayakDaily reported that DUS confirmed the design-and-build tender is still live, with Surat Setuju Terima (SST) targeted for Q1 2027 and completion in 2032. The displayed value stays RM1.52 billion.

Source: DayakDaily — SST Q1 2027; 2032 completion (Oct 2026)
EnablerUtilities

Miri CCGT Power Plant

UKAS reported that the 500MW Miri CCGT project reached 63 percent completion as of the third quarter of 2026. Commercial operations remain targeted for the end of 2027. The displayed value stays RM2 billion; UKAS also stated RM2.5 billion, which is held for manual review.

Source: UKAS — Miri CCGT 63 percent complete as of Q3 2026 (Oct 2026)
SectorForestry

Greenhouse Gas Emission Ordinance 2023

UKAS announced an RM20 million RMK-13 allocation for GHGMS Phase 2. Phase 2 operations and annual verified emissions reporting remain open.

Source: UKAS — RM20 juta GHGMS Fasa 2 (Oct 2026)
EnablerBasic Infrastructure

Coastal Road Network & Second Trunk Road

The Sejingkat Bridge opened to the public on 5 October 2026 after a soft-opening ceremony. Contractual completion on 22 October and the rest of the CSTR programme remain open. The remaining nine major bridges are targeted for late 2027.

Source: DayakDaily — Sejingkat Bridge opened to the public (Oct 2026)
EnablerTransport

Kuala Baram Capital Dredging

Miri Port Authority said the Kuala Baram dredging project had reached about 90 percent physical progress on 21 September 2026 and was ahead of the contract schedule. Completion is expected by the end of 2026.

Source: DayakDaily — About 90% physical progress (Sep 2026)
EnablerInnovation

Sarawak Bioindustrial Park

Construction of the Sarawak Bioindustrial Park Central Hub officially commenced after the foundation-laying ceremony, and BioVerde exchanged eight industry collaboration agreements and MoUs. The 24-month construction period targets completion in August 2028. Anchor and research partner selection remains open where partners are still exploring facilities.

Source: DayakDaily — Eight industry collaboration agreements exchanged (Aug 2026)
EnablerRenewable Energy

Baleh Hydroelectric Project

POWERCHINA reported that first-bay concrete for the Baleh dam face slab was poured on 10 August 2026, marking the start of main face-slab construction. Reservoir impoundment from September 2027 and later generation milestones remain open.

Source: POWERCHINA — Baleh dam face-slab concrete pour began (Aug 2026)
EnablerInnovation

Sarawak Science Centre (SSCiEX)

The five-storey Sarawak Science Centre officially launched with 22 thematic galleries and more than 400 hands-on exhibits, before opening to visitors on 30 July.

Source: SSCiEX - Current facility and visitor opening
EnablerInnovation

Kota Petra Green Technology Park

A RM328 million EPCC contract was awarded for the 100MWac agrivoltaic solar facility in Phase 1, marking the project's move from approvals and site preparation into execution.

Source: The Star - RM328M Phase 1 EPCC contract (Jul 2026)
SectorCommercial Agriculture

Lubok Punggor AgriHub and Irrigation Project

Compensation totalling RM6.5 million was handed to 119 recipients for the Lubok Punggor AgriHub development, whose scope includes irrigation, drainage, a reservoir, warehouse and machinery workshop.

Source: UKAS - AgriHub compensation and construction scope (Mar 2026)
SectorForestry

Sarawak Reef Ball Project

At the Phase II final deployment ceremony in Kabong, Sarawak Forestry Corporation said all 5,000 Phase II reef balls had been deployed along the Sarawak coastline. Phase II programme completion in 2027 remains open for monitoring and socio-economic studies. The later July 2026 Kuala Nyalau 80-unit drop is recorded separately as continuing activity.

Source: Borneo Post — Phase II final deployment; all 5,000 reef balls deployed (Sep 2025)